2021 Street Reconstruction Project 21-1 – 3.0 miles of local streets (from 127th Avenue north of 130th Lane between Shenandoah Boulevard and Hanson Boulevard plus Bluebird Circle north of 121st Avenue)
The Contractor for this project is New Look Construction. The Contractor’s main contact is Adam Pohlkamp at 320-980-3637. The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).
Next week in Area 2 (streets including 128th Avenue, Nightingale Street, Jay Street, and 129th Lane), crews will wrap up remaining sod installations.
In Area 3 (streets including 127th Avenue, 127th Lane, 127th Circle, Nightingale Street Cul-de-sac, Killdeer Street, Ibis Street, the remaining section of 128th Avenue not included in Area 2, Grouse Street, and Bluebird Circle), asphalt driveway restorations have been rescheduled to take place on Monday and Tuesday (August 30 and 31). Mailbox reinstallations for Area 3 have also been shifted to now take place on Monday (8/30). Boulevard restorations in Area 3 will begin next week.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS:
If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Zach Pfieffer at zpfieffer@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.