2021 Street Reconstruction Project 21-1 – 3.0 miles of local streets (from 127th Avenue north of 130th Lane between Shenandoah Boulevard and Hanson Boulevard plus Bluebird Circle north of 121st Avenue)
The Contractor for this project is New Look Construction. The Contractor’s main contact is Adam Pohlkamp at 320-980-3637. The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).
Next week in Area 2 (streets including 128th Avenue, Nightingale Street, Jay Street, and 129th Lane), crews will continue boulevard restorations consisting of irrigation repairs, and topsoil/sod placement.
In Area 3 (streets including 127th Avenue, 127th Lane, 127th Circle, Nightingale Street Cul-de-sac, Killdeer Street, Ibis Street, the remaining section of 128th Avenue not included in Area 2, Grouse Street, and Bluebird Circle), asphalt pavement reclamation will take place on Monday (8/16). Concrete curb and driveway replacements will continue through Tuesday (8/17).
Roadway sub-cutting and gravel base tolerancing will begin on Tuesday and continue through the end of the week. Roads will be congested during this process. Property owners are asked to be patient while the work takes place and allow construction vehicles to safely get out of the way during the work. Access will be interrupted between driveways and certain Area 3 street segments at times, and the specific locations of this work will consistently change throughout the day.
Asphalt roadway paving in Area 3 is expected on August 25, with asphalt driveway restorations planned for August 26 and 27. Boulevard restorations will then take place during the week of August 30.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS:
If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Zach Pfieffer at zpfieffer@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.