2021 Street Reconstruction Project 21-1 – 3.0 miles of local streets (from 127th Avenue north of 130th Lane between Shenandoah Boulevard and Hanson Boulevard plus Bluebird Circle north of 121st Avenue)
The Contractor for this project is New Look Construction. The Contractor’s main contact is Adam Pohlkamp at 320-980-3637. The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).
Work next week includes roadway grading in Area 2 (streets including 128th Avenue, Nightingale Street, Jay Street, and 129th Lane) to prepare for asphalt paving. Grading work is expected to be complete by mid next week. Asphalt paving in Area 2 is planned for July 29. Asphalt driveway restorations in Area 2 are expected to take place on Monday, August 2.
Work next week in Area 3 (streets including 127th Avenue, 127th Lane, 127th Circle, Nightingale Street Cul-de-sac, Killdeer Street, Ibis Street, the remaining section of 128th Avenue not included in Area 2, Grouse Street, and Bluebird Circle) includes completion of storm sewer catch basin replacements. Curb removals will also take place next week throughout Area 3.
The Contractor has received City approval to work in Area 3 between 8 am and 2 pm on Saturday, July 24 to continue storm sewer catch basin replacements.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS:
If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Zach Pfieffer at zpfieffer@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.