2021 Street Reconstruction Project 21-2 – 3.6 miles of local streets (streets north of Coon Rapids Boulevard between Flamingo and Jay Streets north to 106th Avenue, Eagle Street to Avocet Street south of Egret Boulevard, and the neighborhood off Foley Boulevard between 95th and 97th Lanes)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher, who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work planned for the week of June 28 includes asphalt base course paving in Phase 1 of Area 1 (streets including Flamingo Street, Grouse Street, Hummingbird Street, and a portion of 104th Avenue).
Asphalt pavement reclamation and remaining curb and driveway removals will take place next week on streets within Phase 2 of Area 1 (street including Ibis Street, Jay Street, 106th Avenue, and a portion of 104th Avenue). All driveways will be backfilled with gravel to maintain access to properties.
Work in Area 3 (streets east of Foley Boulevard and north of TH 610 up to 97th Lane) next week includes preparation for permanent watermain installations and temporary water service connections on streets including 97th Lane, 97th Avenue, Flintwood Street and a portion of 95th Lane.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS:
If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Jason Huebscher at jhuebscher@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.