2021 Street Reconstruction Project 21-1 – 3.0 miles of local streets (from 127th Avenue north of 130th Lane between Shenandoah Boulevard and Hanson Boulevard plus Bluebird Circle north of 121st Avenue)
The Contractor for this project is New Look Construction. The Contractor’s main contact is Adam Pohlkamp at 320-980-3637. The City’s full-time project inspector is Zach Pfieffer, who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).
Asphalt paving originally planned for this week in area 1 (streets in the northwest corner of Shenandoah Oaks including 128th Lane, 129th Lane, 130th Lane, Nightingale Street, Martin Street, and Linnet Street) has been rescheduled to take place next week on Wednesday and Thursday (June 9 and 10). Notifications for the paving operations will be distributed to area 1 property owners on June 8. Boulevard restorations will begin in area 1 shortly after the paving work is complete.
In area 2 (streets including 128th Avenue, Nightingale Street, Jay Street, and 129th Lane), utility work including valve and hydrant replacements is now expected to begin by mid next week (June 9) and continue through the following week.
ATTENTION RESIDENTS PLANNING ON FULL DRIVEWAY REPLACEMENTS:
If a portion of your driveway apron has been removed as part of the City’s construction project and you are planning to have your own contractor install a full new driveway, please email Zach Pfieffer at zpfieffer@coonrapidsmn.gov with details (property address, timing of installation, etc.). The City will work with you to issue a credit for the work that would have been completed under our project and will direct the City’s Contractor to exclude your driveway apron from its restoration plans.