2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Final cleanup including signing and striping, as well as asphalt pavement joint sawing and sealing, will take place in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street) and Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue) within the next couple of weeks.
Paving planned to take place in area 3 (97th Avenue near Yellowpine Street), is now planned for the end of next week.
Due to weather conditions this week, remaining paving work planned in the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane), which includes asphalt base paving, has been delayed until next week. Boulevard reestablishments and irrigation repairs will be completed immediately following street paving.