2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work planned for the week of September 21 includes final wear course paving on streets within Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue). After this work is complete, the final signing and striping will be installed.
No work is planned to take place next week in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street).
In Area 3 (97th Avenue near Yellowpine Street), irrigation and boulevard restorations will take place.
Work planned in the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane) includes watermain service installations on 108th Avenue (if any remain to be completed after this week) and 108th Lane. Roadway grading and preparations for curb installation will take place on Kumquat Street and 107th Lane.