2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work planned for the week of September 14 includes completion of sod installations by late Tuesday in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street). Topsoil placement will take place in this area on Saturday, September 12. Final wear course pavement is tentatively scheduled for the week of September 21.
Miscellaneous concrete and cleanup work will carry over into next week in Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue). Final wear course pavement is tentatively scheduled for the week of September 21.
In Area 3 (97th Avenue near Yellowpine Street), placement of the asphalt base course is now planned for early next week.
Work planned in the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane) includes continued watermain and water service installations on 107th Lane and Norway Street. Work will take place on Kumquat Street which includes storm sewer installations, pavement reclamation, and roadway grading.