2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue)
The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).
Work planned for the week of August 24 includes boulevard and asphalt driveway restorations in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street). The Contractor plans to work this Saturday (August 22) to further restore the area to the maximum extent possible before school starts in early September at Hamilton Elementary.
No work is planned next week in Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue). Sod was installed during the week of August 17.
In Area 3 (97th Avenue near Yellowpine Street), roadway grading will be complete, and installations of new concrete curb and gutter will take place.
Work planned in the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane) includes continued progress on the temporary and permanent watermain systems.