Coon Rapids Boulevard Reconstruction Project 18-13 – Reconstruction of Coon Rapids Boulevard from Egret Boulevard to the East River Road/Coon Rapids Boulevard Split 

Coon Rapids Boulevard is an Anoka County Highway Department owned and maintained roadway, however this reconstruction project is being led by the City of Coon Rapids. Please direct all questions and concerns regarding this construction project to Mark Hansen, City of Coon Rapids Project Manager and City Engineer. Mark can be reached at 763-767-6465. The Contractor for this project is S.M. Hentges & Sons, Inc. The Contractor's main contact is Joe Miller.

Roadway work next week includes installations of new concrete curb and gutters in the median areas of north and southbound Coon Rapids Boulevard (was originally scheduled for the week of August 3). Work on the new concrete median barriers from the Coon Rapids Boulevard bridge north is tentatively planned to start next week.

Bridge rehabilitation work will continue all next week in both the north and southbound directions of Coon Rapids Boulevard over the BNSF railroad tracks and East River Road. 

2020 Street Reconstruction Project 20-1 – 2.6 miles of local City streets (streets near Norway Street and East River Road, 97th Avenue near Yellowpine Street, Norway Street near 107th and 108th Lane, and Avocet Street near 111th Avenue) 

The Contractor for this project is Northdale Construction. The Contractor’s main contact is Kevin Topp at 320-493-7369. The City’s full-time project inspector is Jason Huebscher who can be contacted any time to respond to specific questions or concerns. Jason can be reached at 763-767-6570 (office) or 612-709-2704 (cell).

Work planned for the week of August 10 includes boulevard restorations (topsoil and sod placements) in Area 4 (streets east of East River Road – 89th Avenue, Norway Street, and 86th Avenue).

Concrete curb and gutter and driveway replacements will be finished in Area 1 (Avocet Street, 109th and 111th Avenue, 109th Lane, and Xeon Street). The Contractor will also be grading the roadways to prepare for asphalt paving the week of August 17.

In Area 3 (97th Avenue near Yellowpine Street), work will include roadway grading and removals of remaining curb and gutters.

Work planned in the Autumn Knolls neighborhood (Area 2 – Norway Street near 107th Lane and 108th Lane) includes construction of the new watermain systems. 

2020 Street Reconstruction Project 20-2 – 2.3 miles of local and MSA streets (streets near 113th Avenue and Crooked Lake Boulevard, Crooked Lake Boulevard north of Northdale Boulevard to Gladiola Street, and Riverdale Drive and Northdale Boulevard) 

The Contractor for this project is Douglas Kerr Underground. The Contractor’s main contact is Ryan Kerr at 320-515-0046. The City’s full-time project inspector is Zach Pfieffer who can be contacted any time to respond to specific questions or concerns. Zach can be reached at 763-767-6431 (office) or 612-710-8243 (cell).

Work planned for the week of August 10 includes boulevard restorations on 113th Avenue.

Work on Crooked Lake Boulevard next week includes storm sewer construction and roadway base grading.

Asphalt paving on the west side of Riverdale Drive is expected to be complete on Monday. New sidewalk construction is also planned on the west side of Riverdale Drive, and will continue throughout the week.  

2020 Street Reconstruction Project 20-3 – 2.3 University Avenue north of Main Street (City of Blaine Project) 

This project is being administered by the City of Blaine. The Contractor for this project is Dresel Contracting. Project contact information and schedule will be sent via US Mail and posted on the City of Coon Rapids website once available. If property owners have questions regarding the construction process and schedule, please contact Stefan Higgins at 763-717-2722 at the City of Blaine, or Mark Hansen at 763-767-6465 at the City of Coon Rapids. 

Work planned for University Avenue during the week of August 10 includes paving of the asphalt base course. Boulevard re, including irrigation repairs, will follow placement of asphalt. 

Anoka County Projects – Hanson Boulevard (CSAH 78) Railroad Bridge Overpass, and Hanson Boulevard from Northdale Boulevard (CSAH 11) to Main Street (CSAH 14)

Hanson Boulevard is a County road in Coon Rapids (north of Coon Rapids Boulevard). Chris Osterhus is the County’s Construction Supervisor and can be contacted at 763-324-3189.

To view the County’s updates and subscribe to email notifications, click here: http://www.anokacounty.us/1578/Construction-Weekly  

Watch our Videos!   

Watch the City’s street reconstruction videos to learn more about the process! The first addresses frequently asked questions, and the second demonstrates what the process will look like in a Coon Rapids neighborhood.

Visit our website to view them: www.coonrapidsmn.gov/843/Street-Reconstruction

Report It
Share on Facebook
Share on Twitter
Share via Email

Published by the City of Coon Rapids, Minnesota * Copyright 2020
11155 Robinson Drive, Coon Rapids, MN 55433

Powered by
CivicSend - A product of CivicPlus